The current version indicator (a Blue gear on a process revision icon) Current process revision icon is a visual indicator to be used as part of your own procedures if desired. (The Blue indicator is also used as a flag for some FactoryLogix xTend integrations.)

  1. Log into the NPI client application.

  2. Select Home > Process Engineering.

  3. In Define Processes, select the Open Process Open Process button button (the folder).

  4. Find and select the process you want to mark as current in the Please Select a Process Revision dialog.


    Please Select a Process Revision dialog


  5. Select the Mark Process Revision as Current Mark Process Revision as Current button.png button at the top of the window, then select Yes when the confirmation dialog displays.


    Are You Sure dialog



    Notice that the icon for the process revision now includes a Blue "gear": Current process revision icon


    Current process revision


Note

A process with a Green gear Latest created process revision icon icon indicates the latest process revision created for an assembly.